Charlie Pump Station – Dallas, TX

By March 29, 2022October 7th, 2022Latest News, Latest News 2022

This project began in March, 2022 with a target completion date of 4.2 years. It was awarded to LGC through its border wall MATOC award with a scope of work as follows: Construction of a pump station with the capacity to collect and pump 225,000 gpm of storm water over the West levee of the Dallas Floodway and into the floodway. It consists of but not limited to constructing a pump house with three 75,000 gpm pumps, and pipes to go up an over the levee. LGC will provide the design services, specifications, drawings and construction documentation. We will provide labor, materials, equipment, supervision, testing and shop manufacturing and all transportation necessary to perform the project requirements. LGC has teamed up with highly qualified subcontractors from CP&Y, Inc. headquartered in Dallas, and Eagle Contracting LP, a Fort Worth, TX based company Contract Value $63,555,380